The métrovision network
Montreal, 27 September 2004 – The métrovision screens will be installed on the platforms of 16 of Montreal’s main métro stations. The work will be carried out in 3 phases. Once rollout is completed, 85% of métro clients will have the opportunity to consult the giant screens during their commutes.
Phase 1
September 2004.
Berri-UQAM - Installation of 22 screens on the station’s 3 lines
(1 - Green, 2 - Orange and 4 - Yellow)
Phase 2
January to December 2005
Planned rollout of 78 screens in 12 stations of the métro system
|
|
Phase 3
January to December 2006
Planned rollout of 40 screens.
- Jean-Talon
- Lionel-Groulx
- Square-Victoria
- 30 -