Upcoming work at Laurier station

Project summary

Starting June 28, 2021, we will begin work on the north entrance building of Laurier station, on Laurier Avenue East.


Duration of the work: June 28, 2021, to mid-November 2021

Description of the work:

  • Renovation of one interior wall and two exterior walls
  • Floor slab renovation
  • Roofing work on the entrance building
  • Turnstile layout redesign

Métro impacts:

The station will remain open at all times.

From August 8 to 25, 2021, the north entrance building of Laurier station, located on Laurier Avenue East, will be closed temporarily to undergo renovations. The station entrance on Saint-Joseph Boulevard at the corner of Berri Street will remain open during this time.

Bus impacts: No

Impact on customer trips

Texte important

The station will remain open during the work.

North entrance building closed August 8 to 25, 2021

The north entrance building of Laurier station, located on Laurier Avenue East, will be closed temporarily from August 8 to 25 to undergo renovations. The station entrance on Saint-Joseph Boulevard at the corner of Berri Street will remain open during this time.

Work at Laurier station

Impact on local residents

The work will take place mainly inside the entrance building. We will be renovating walls and upgrading the turnstile area by adding new turnstiles and a fare gate to improve customer flow within the station.

Part of the structural slab will be demolished from the outside, and we will conduct some work on parts of the entrance building roof. A worksite will be set up outdoors in the small public space next to the entrance building. Occasionally, the work may generate noise that may be heard near the worksite. In accordance with municipal by-laws, this work will be conducted Monday to Friday, between 7 a.m. and 7 p.m.

 