Préfontaine

Work completed at Préfontaine station

Project summary

Roof refurbishment work at Préfontaine station is now complete.

Duration of the work: November 7 to end of november 2022

Description of the work: Renovation of both entrance building roofs

Métro impacts: None

Bus impacts: None

Impact on customer trips

The work is now complete and there are no longer any obstructions around the station.

Impact on local residents

The work is now complete, and there are no longer any impacts for local residents.

Learn more about the project

This project included the following phases:

  • Demolishing the existing rooftop waterproofing system
  • Removing and reinstalling rooftop mechanical equipment
  • Installing the new rooftop waterproofing system
  • Replacing the roof drains