Work completed at Monk station
Project summary
Roof refurbishment work at Monk station is now complete.
Duration of the work: October 24, 2022 to end of november 2022
Description of the work: Renovation of both entrance building roofs
Métro impacts: None
Bus impacts: None
Impact on customer trips
The work is now complete and there are no longer any obstructions around the station.
Impact on local residents
The work is now complete, and there are no longer any impacts for local residents.
Learn more about the project
This project included the following phases:
- Demolishing the existing rooftop waterproofing system
- Removing and reinstalling rooftop mechanical equipment
- Installing the new rooftop waterproofing system
- Replacing the roof drains