Réno métro - Beyond the works sites is tomorrow's network

A stronger network

RENOVATION OF THE INSTALLATIONS
Regular maintenance of the stations based on the useful life of their components and infrastructure ensures proper maintenance of the network.

STATIONS NATURE OF THE WORK START – END
Villa-Maria Major repairs - Closure of the station Completed in 2011
Du Collège Major repairs -
Closure of the north entrance
Closure of the south entrance

Completed in 2011
Completed in 2010
Assomption Major repairs Completed in 2010
Côte-Vertu Major repairs
- Phase 1: Closure of Côte-Vertu south entrance
- Phase 2: Closure of Édouard-Laurin entrance
Completed in 2010
Côte-Ste-Catherine Major repairs - Closure of the station Completed in 2010
Place-Saint-Henri Closure of the main entrance Completed in 2010

 

REMOVAL OF WATER FROM THE ARCHWAYS
The removal of water infiltration from the archways makes the métro cleaner and safer.

REPAIR OF THE DRAINAGE SYSTEM
STATIONS DATES
Crémazie, Laurier, Côte-Vertu, De la Savane, Rosemont, Namur, Monk, Beaubien, De L’Église, Du Collège  2011

 

REPLACEMENT OF VENTILATION STATIONS
Eighty-five mechanical ventilation stations spread out along the métro lines provide emergency ventilation and a comfortable trip for transit users. Certain of these stations require repair or replacement.

NAME OF STATION BETWEEN THE FOLLOWING STATIONS START – END
Bélanger station Jean-Talon and Bélanger Completed in 2011
Providence station Berri-UQAM and Sherbrooke Completed in 2011
Dickson station Assomption and Cadillac Completed in 2011

This work is being carried out thanks to financing of up to 75% provided by Transports Québec.